When you’re building your forever home, the details matter—including how you’ll use the garage.
Our customer in Surprise, Arizona, is a local realtor who has helped design the home he’s always wanted. His three-car garage will include a home gym, and his family’s goal is a comfortable workout space around 75°F during the summer.
Sapper HVAC completed the rough-in phase for a planned 3-ton mini-split before insulation, drywall, and exterior stucco are installed.
With the wall framing still open, we routed the refrigerant lines, condensate drain, and communication wiring inside the wall. That planning keeps the main line-set run concealed instead of running it down the finished exterior wall.
The photos show this first stage: exposed framing, the concealed line route, and the outdoor connection point waiting for the equipment installation.
This project is still underway. We expect to return in approximately two weeks to install the equipment and complete startup and commissioning. The homeowner’s 75°F target is the comfort goal; the system is not operating yet.
Rough-in progress photos

Work in progress: concealed mini-split line routing at the Surprise new build.

Work in progress: concealed mini-split line routing at the Surprise new build.

Work in progress: concealed mini-split line routing at the Surprise new build.

Work in progress: concealed mini-split line routing at the Surprise new build.

Work in progress: concealed mini-split line routing at the Surprise new build.
Building a new home or planning a garage gym? Bring garage cooling into the conversation before the walls are closed so equipment placement and line routing can be planned together.